UPDATE: December 7th
- Hyperia Transfer Track And Banked Turn out of station Installed


UPDATE: December 4th
- Here are some Hyperia pictures taken by the construction crew at Thorpe Park




UPDATE: November 29th
- Vertical construction continues on Hyperia at Thorpe Park
- The splash down has now been installed



UPDATE: November 19th
- Break Run and final element of the ride is done, supports have also been added closer towards the lift hill base.




UPDATE: November 14th
- Latest track and station work update from within Hyperia’s construction site






UPDATE: October 25th
- The latest on the track sections for Hyperia






UPDATE: October 21st
- Build on the second part of the outerbank turn ongoing
- Steelwork added to station
- upright steels started on maintenance building




UPDATE: October 16th
The station has started to be built, as well as more track and supports for Hyperia going into place!

Let us know your thoughts on Hyperia by leaving a comment below.



We will inform you of further updates on HYPERIA as they take place.
Sign Up
Make sure you sign-up below for all the latest Hyperia news and Thorpe Park offers straight to your inbox.
Follow UK Theme Park Spy:










Conversation
The opinions and views shared in the comments section belong solely to the individual users and do not reflect those of UK Theme Park Spy. UK Theme Park Spy does not endorse, support, or guarantee the accuracy of any content posted by users.